Question
The first step in planning and scheduling a project is to develop the __________.
Student Answer: 
employee scheduling plan
PERT/CPM network diagram
critical path
work breakdown structure
variance calculations for each activity
Question 2. The critical path of a network is the:
Student Answer: 
shortest time path through the network.
path with the fewest activities.
path with the most activities.
longest time path through the network.
none of the above.
Question 3. PERT:
Student Answer:...
- Exam (elaborations)
- • 20 pages's •
-
GBA334 Final Exam Latest 2018•GBA334 Final Exam Latest 2018
Preview 1 out of 20 pages
Question
The first step in planning and scheduling a project is to develop the __________.
Student Answer: 
employee scheduling plan
PERT/CPM network diagram
critical path
work breakdown structure
variance calculations for each activity
Question 2. The critical path of a network is the:
Student Answer: 
shortest time path through the network.
path with the fewest activities.
path with the most activities.
longest time path through the network.
none of the above.
Question 3. PERT:
Student Answer:...
Question
Question 1 
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, what is the PERT variance for this activity?
Question 1 options:
2.33
5.44
64.00
8.00
None of the above
Question 2 
Given the following small project, the critical path is __________ days.
Question 2 options:
none of the above
14
10
20
16
Question 3 
The expected time in PERT is:
Question 3 options:
the square root of the sum of the variances of the activities on t...
- Exam (elaborations)
- • 23 pages's •
-
GBA334 Final Exam Latest 2018•GBA334 Final Exam Latest 2018
Preview 1 out of 23 pages
Question
Question 1 
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, what is the PERT variance for this activity?
Question 1 options:
2.33
5.44
64.00
8.00
None of the above
Question 2 
Given the following small project, the critical path is __________ days.
Question 2 options:
none of the above
14
10
20
16
Question 3 
The expected time in PERT is:
Question 3 options:
the square root of the sum of the variances of the activities on t...